Environmental Legislation Website This Page Last Updated 7 April, 2011

Navigational Interference - Installations

Legislation Consent Performance Standards Monitoring Reporting Non compliance Renewal Pending legislation Snippets
Print Page
Legislation Back to Top
Key Legislation

Licensing provisions of the MCAA and Marine Scotland Act will come into force in April 2011 and will disapply the Coast Protection Act. MCAA will include navigational provisions, but virtually all activities associated with exploration or production/storage operations will not require licences.

The provisions of the Coast Protection Act therefore transferred to the Energy Act 2008 Part 4A by the MCAA and MSA to cover navigation considerations relating to exempted exploration or production/storage operations. Consent to locate provisions of the Energy Act Part4A will come into force in April 2011.

DECC is about to consult on the Part 4A consenting provisions, which will provide an opportunity to update the Coast Protection Act regime currently being implemented on behalf of the Department of Transport (see Pending Legislation)

Supporting legislation
Guidance (to be updated with new requirements once new DECC guidance is issued - see Pending Legislation)
Consent Needed and How to Obtain It Back to Top
Consent Needed (to be updated with new requirements once new DECC guidance is issued - see Pending Legislation)

Offshore oil and gas installations may only be located with prior written consent. At present there are 6 types of CPA Consent:

  • CPA1 - Drilling
  • CPA2 - Permanent Structures
  • CPA3 - Pipeline Works Authorisation (see Navigational Interference - Pipelines)
  • CPA4 - Cables
  • CPA/DISP - Dispensations
  • CPA/WA - Well Abandonment Operations

There are also specific requirements around navigational issues for decommissioning programmes (see Decommissioning - Navigation)

How to Apply

Application in writing.

In considering an application for consent DECC has to evaluate the risk to shipping which may arise from the installation of facilities of all kinds including pipelines, and measures to reduce such risks. The following aspects are considered:

  • Evidence of shipping movements close to the proposed locations;
  • Likely changes in those movements resulting from an installation;
  • Constraints imposed upon local navigation by the installation;
  • Danger of passing vessels colliding with the installation;
  • The increased danger of ships colliding with each other, or having other misfortune, as a result of needing to avoid the installation; and
  • If appropriate the scope for reducing risk by taking counter measures.

Guidance on the application process is available on DECC website and from the DECC CPA Process Flowchart

Application for a consent under the CPA can also be made through the PON15 application process for some operations (see Drilling Chemicals and Workover as appropriate). For pipelines, consent to locate is through the PWA application (see Navigational Interference - Pipelines)

Who to Apply to

DECC Licensing and Consent Unit (DECC LCU-OED) by email at emt@decc.gsi.gov.uk

If applying by PON15 these must be submitted electronically to DECC via the UK Oil Portal. Operators will need to be registered with DECC for access to the Portal.

To set up a UK Oil Portal Account, contact the DECC OED Environmental Management Team at ukop@decc.gsi.gov.uk

Any problems with PON15 submission contact the DECC OED EMT by email at emt@decc.gsi.gov.uk

Note: DECC took over responsibility for the Coast Protection Act 1949 Regulations for offshore oil and gas installations in October 2005.

When to Apply

Fixed installations - consent applications should be submitted a minimum of 28 days in advance of the proposed activities. For busier or higher risk locations is is recommended that earlier applications be made to give time to address any queries made by DECC and/or consultees.

Mobile installations - 28 days prior to mobilisation of rig.

Pipelines - consent to locate is triggered and issued as part of the Pipelines Work Authorisation application (see Navigational Interference - Pipelines)

Performance Standards Back to Top
Fixed Installations

It is preferred and less problematic to operators and DECC if applications for new developments address all the facilities to be placed rather than a series of piecemeal applications. Consent can then be given to cover the whole operation e.g. template, drilling, jacket, topsides, pipelines etc. Difficulty has arisen in the past for some operators where uncontroversial seabed works have been put forward for consent before and without details of more sensitive surface works. A limited consent e.g. for exploratory drilling only does not imply that consent will necessarily be given for other operations at the same site.

Deep Water Routes and Traffic Separation Schemes

Consent to locate in such areas are unlikely, and if consent is given stringent conditions limiting the time allowed on site are likely to be imposed.

Dynamically Positioned Vessels

CPA consents to locate will not be required for activities involving the use of vessels maintained on station using dynamic positioning, where the vessel would be able to move off station in the event of a navigational emergency, and where the proposals will not involve any deposit or removal of materials from the seabed that would constitute a locus for application of the Coast Protection Act (CPA).

Further information available from CPA Guidance Notes for Vessels - Interim on DECC website
General Consent to locate may include conditions to minimise interference with navigation or fishing. For example, conditions are likely with respect to decommissioning requirements.
Decommissioning There are specific marking and notification requirements for decommissioning programmes. More detail available in Decommissioning - Navigation
Sampling/Monitoring Requirements Back to Top
Monitoring

Not applicable

Reporting Requirements Back to Top
What to Report (to be updated with new requirements once new DECC guidance is issued - see Pending Legislation)

Reporting of offshore installation movements.

How to Report

Report using Annex A of HSE Offshore Safety Division Operations Notice No 6.

Who to Report to DECC and MCA. 
When to Report

At least 48 hours before installation tow-out is commenced. 

Non Compliance Back to Top
What to do if in Breach of Consent/ Authorisation (to be updated with new requirements once new DECC guidance is issued - see Pending Legislation)

Section 36 of the Coast Protection Act 1949 makes non-compliance with the requirements of Section 34 or any conditions imposed within consents granted an offence. The Minister of Transport may serve notice to remove works or make alterations within a stated period (not less than 30 days). 

Offshore Inspection The DECC Environmental Inspectorate Enforcement Policy sets out the general principles that Inspectors shall follow in relation to enforcement including prosecution.
Renewal and Variation Back to Top
Renewal Not applicable
Pending Legislation Back to Top

Energy Act Part 4A - expected provisions for navigation and consent to locate

The changes will introduce a formal application process which will be linked to the environmental regime instead of the Petroleum Act or Energy Act consenting regimes, e.g. consent to locate a pipeline will be linked to an ES or PON15C application process rather than the PWA process.

There will be no formal requirement for an ES to support applications for consent, but related ESs will be copied to the relevant navigational bodies (e.g. MCA, Lighthouse Authorities, MOD, FIshermen's representative bodies) to confirm there are no significant issues.

Consultation period for applications will be 28 days to match other environmental processes.

Some vessel activities will require a consent to locate, if the vessels will be physically connected to seabed infrastructure that could constrain their ability to "navigate" e.g. drill ships and intervention vessels.

Consent documents will include enforceable conditions, and depending upon the nature of the application, these could include:

  • Existing marking/lighting guidance documents attached to current (DfT) consents;
  • Lighthouse Authority requirements including inspection regimes;
  • MOD requirements including the use of beacons (to replace the Model Clause conditions)
  • Guard vessel requirements
  • Vessel logs and reporting requirements

Where appropriate the consent requirement and compliance with the consent conditions will be included in teh remit of offshore enviornmental inpsections, and powers will be available to enforce compliance and pursue any offences.

The consents will cover the duration of the deployment, and not just the duration of any installation operations, e.g. installations and pipelines will have a "life" consent that will be surrendered when the infrastructure is removed or a MCAA licence issued that includes insitu abandonment.

Applications to vary the consent will be rquired, including variations that relate to activities within an existing 500 meter safety zone e.g. it will be necessary to vary the consent to locate a rig or flotel within the safety zone of a consented installation.

There is currently no charging powers so there will not be a separate consent to locate fee.

 

Snippets Back to Top
 

None at present

 

Uncontrolled copy when printed
Site produced and edited by Xodus AURORA