ES Required
|
|
No ES Required
|
Action Needed
|
|
>12 months (depends on size of development)
|

|
-
|
|
Determine requirement for an
Environmental Statement (ES). An ES is mandatory for installation of a pipeline that is
greater than 40 km in length and 800 mm in diameter and so this step can be skipped. Many
smaller pipelines may form part of a wider development where an ES
will be required (see New Projects).
In this case the pipelines will be included in the wider development ES/PON15D submission
and so a PON15C need not be submitted to determine requirement for
an ES.) |
|
Undertake Environmental Assessment (EA) and prepare ES.
|
 |
Undertake informal consultation with statutory consultees,
DECC, JNCC and FRS/CEFAS.
|
 |
Undertake early consultation with fishing interests
|
 |
Identify if development occurs in vicinity of any habitats
or protected species under EU Habitats Directive. Additional measures
and an Appropriate Assessment may be required.
|
|

|
Prepare environmental information (and possibly chemical
permit application) section of PON15C.
|
|
n/a
|
4-5 months
|
|
4 months
|
4 months
|
 |
Submit Pipeline Works
Authorisation, which includes application for Consent
to Locate
|
|
n/a
|
 |
Submit ES
along with Pipeline Works Authorisation.
|
|
3 months
|
3 months
|
 |
Submit application for Consent
to Deposit Materials for any material deposits required
for pipeline stabilisation.
|
 |
Prepare and submit application for
Chemical Permit (PON15C) for any chemicals to be used
and discharged during pipeline commissioning.
|
|
Pipeline Construction
|
|