ES Required
|
|
No ES Required
|
|
|
>12 months (depends on size of development)
|

|
As early as possible
|
|
Determine requirement for an
Environmental Statement (ES) by submission of PON15D
(Note: An ES is mandatory for new or increased production of over
500 tonnes of oil or 500,000 m³ gas per day and so this step
can be skipped).
|
 |
Undertake informal consultation with statutory consultees,
DECC, JNCC and FRS/CEFAS.
|
 |
Identify if development occurs in vicinity of any habitats
or protected species under EU Habitats Directive. Additional measures
and an appropriate assessment may be required.
|
|
n/a
|
 |
Undertake Environmental Assessment (EA) and prepare ES.
|
|
6 months
|

|
Apply in writing to DTLR for Consent to Locate for fixed
installation
|
|
n/a
|
 |
Prepare environmental information section of PON15D.
|
|
n/a
|
4 months
|
 |
Submit PON15D
along with Application for Consent (PON16).
|
|
3 months
|
n/a
|
 |
Submit ES along with Application
for Consent (PON16).
|
|
Project Approval
|
|