Environmental Legislation Website This Page Last Updated 29 October, 2008

Well Test - Consent Requirements

Well Test

 

Extended Well Test

Action Needed

n/a

9 months

Determine requirement for an Environmental Statement (ES) by submission of environmental information sections of PON15*.
   

If ES is required, undertake environmental assessment (EA) and prepare ES.

4 months

4 months

If no asset-wide Oil Spill Contingency Plan in place, prepare OSCP.

n/a

3 months

Submit ES along with Application for Consent for Test Production (PON16) for extended well test .

2 months

2 months

Submit OSCP (if needed) to DECC for approval.

Welltest

* PON15B for well test from MODU and PON15D for platform or within 500 m of platform

Key Compliance During Well Test

Use efficient burners and consider the need for well test.

Continually monitor the operation and stop operation if oil seen on sea surface. Report fall-out to sea as an oil spill to DECC and other oil spill reporting contacts as defined in OSCP.

Ensure an oil pollution response vessel is available, if requested by DECC.

If undertaking extended well test, ensure that the rate of oil production complies with the requirements of the Consent for Test Production.

If undertaking extended well test, make monthly reports to the regulatory authority detailing the previous months extended well test details. Notify regulatory authority of extended well test completion and inform them of production status of well.

If flare drop out occurs during well test operation, cease operations and report oil spill via PON1 to DECC. Note: a permit/exemption is no longer required for flare drop-out.

 

Uncontrolled copy when printed
Site produced and edited by Xodus AURORA