Identify relevant Planning Authority. This will usually be the Local Planning Authority (LPA) in whose jurisdiction the development is proposed.
EXCEPTION: Where a proposal falls under the jurisdiction of the Infrastructure Planning Commission (IPC) in England and Wales for a National Significant Infrastructure Project (NSIP). (eg LNG facilities, underground gas storage facilities or gas reception facilities). |
34 to 38 weeks (minimum)
15 months+ |
|
Determine requirement for Environmental Impact Assessment (EIA) through a process of Screening using the guidelines and threshold criteria set out within the regulations. A formal screening request can be submitted to the LPA to confirm their interpretation of the requirements of the regulations. |
34 weeks (minimum)
14 months +
|
N/A
|
|
Determine scope of EIA through submission of a request for a scoping opinion to the LPA. The scoping process should involve consultation between the developer, LPA, relevant agencies and statutory stakeholders. In adopting a formal scoping opinion the LPA is required to complete this consultation with statutory stakeholders. |
As early as possible
|
|
Identify if development occurs in vicinity of any habitats or protected species under EU Habitats Directive. Additional measures and a Habitats Regulatory Assessment may be required
|
28 weeks (minimum)
12 months +
(depending on size of the development and environmental issues presented by the site eg seasonal impacts such as impacts on breeding birds) |
|
Undertake EIA and prepare Environmental Statement (ES). |
28 weeks |
|
If deemed ‘major development’ under the Planning Act 2008, conduct pre-application consultation. NB Sufficient environmental information should be available to inform this consultation, but the fully completed ES is not a pre-requisite to commencement of this consultation exercise. |
16 Weeks |
|
|
Submit ES along with Planning Application and other relevant documentation to LPA from consideration. |
|
|
Complete necessary advertising for the ES including publishing notice(s) in relevant local newspaper(s) along with notices at the proposed development site.
|
Project Approval
|
|